Annoucement of planned launch of LNG terminal spot capacity allocation procedure for first half of 2024
2023-10-06 | Company news
Klaipėda LNG Terminal Operator (hereinafter - Company) informs natural gas market participants about the planned announcement of the commencement of allocation of LNG Terminal SPOT LNG cargoes capacities for the first half of 2024.
Taking into account the provisions of the approved Regulations, the Company informs about the planned announcement of the invitation to submit applications for the acquisition of LNG Terminal SPOT cargoes capacities:
The opening date and time for request submissions: 13th October 2023 at 13:00 EET.
The closing date and time for request submissions: 20th October 2023 at 13:00 EET.
Taking into account the provisions of the approved Regulations, the Company informs about the planned announcement of the invitation to submit applications for the acquisition of LNG Terminal SPOT cargoes capacities:
- First cargo, 25-26 January 2024 with regasification capacity from 9th January until 17th February (inclusively).
- Second cargo, 2-3 March 2024 with regasification capacity from 18th February until 12th April (inclusively).
- Size of spot cargo: 1 000 000 000 kWh +- 5%. Requests for different size of cargo are considered, however the priority is given to Conventional size of cargo.
The opening date and time for request submissions: 13th October 2023 at 13:00 EET.
The closing date and time for request submissions: 20th October 2023 at 13:00 EET.
PRELIMINARY LNG REGASIFICATION SCHEDULE