Klaipėda LNG terminal LNG regasification capacity for January-February 2025 are now being allocated
2024-10-15 | Company news
Klaipėda LNG terminal operator, KN Energies (hereinafter referred to as the Company), informs natural gas market participants about the allocation of unused LNG regasification capacity of the LNG terminal under the conditions specified below.
Taking into account the provisions of the approved Regulations, the Company informs about the planned announcement of the invitation to submit applications for the acquisition of LNG Terminal spot cargo capacities:
The closing date and time for request submissions is 24th of October 2024, 8:30 EEST.
This capacity is allocated in a principle “first-come-first served”.
Preliminary regasification schedule
Taking into account the provisions of the approved Regulations, the Company informs about the planned announcement of the invitation to submit applications for the acquisition of LNG Terminal spot cargo capacities:
- Size of spot cargo: 940,000,000 kWh ± 5%. Requests for different size of cargo are considered, however the priority is given to Conventional size of cargo.
- SPOT cargo LNG regasification capacity usage period and cargo delivery window:
- LNG regasification period from 1st of January 2025 to 29th of February 2025. Cargo delivery window: 8-9th of February, 2025.
The closing date and time for request submissions is 24th of October 2024, 8:30 EEST.
This capacity is allocated in a principle “first-come-first served”.
Preliminary regasification schedule